Waxie San Diego

Location: San Diego, CA
System Size: 378 kW DC
Completion Date: 11/01/2014

Product:
1,260 Phono solar panels, 16 SMA inverters

Time:
This system was installed within 7 months of signing the contract. All solar panels were installed in a week and a half with another week of electrical work.
Time on site: three weeks.

Project Description:
We share similar values (customer service, accountability, communication) with our client, Waxie. They hardly knew when our team was on site. It was not all roses and there were some issues along the way with equipment. But in the end we completed a month ahead of schedule and not one change order was written. The payback on this system was less than three years.

They were so happy they awarded us another contract of 900 solar panels to be installed on a distribution center in Ontario, CA. We can’t thank Waxie enough for the opportunity and continued invaluable business relationship!

Waxie Ontario

Location: Ontario, CA
System Size: 270 kW DC
Completion Date: 06/22/2015

Product:
900 Solar Panels, SMA inverters

Time:
This system was installed within 10 months of signing the contract. All solar panels were installed in a week and a half with another week of electrical work.
Time onsite: three weeks.

Project Description:
Waxie Sanitary Supply is an iconic 70-year-old company who could have chosen any solar contractor. After extensive research we are humbled and extremely thankful they gave us the opportunity to install on their company headquarters as well as a distribution center in Ontario, CA.

Our focus from the start of our company has always been the customer, similar shared values to Waxie. This was our second installation for Waxie. A year prior we had installed 1,260 solar panels on their headquarters in San Diego, CA. In order to mitigate their day-to-day operations we had scaffolding erected for access the roof and a porta-potty onsite for our crew. They hardly knew when our team was on site. The biggest challenge with this project was getting our plans approved and working with the city of Ontario. Of course, our team stepped up to the challenge and the system was completed three weeks ahead of schedule.

The payback on this system was also less than three years.

We can’t thank Waxie enough for the opportunities and continued invaluable business relationship!